General Manager Update, October 2026

After an extensive and deliberate 23-month long review, on October 5, 2026, the Massachusetts Energy Facilities Siting Board (Siting Board) unanimously voted to approve HMLP’s Reliability Project.

Hingham’s current electric supply is fed via two parallel transmission lines that share support towers in a number of locations and connect to a single substation.  The current configuration exposes the entire system to the possibility of extended power outages due to a single failure, whether it be from increasingly severe weather, equipment damage, or an incident along the active commuter rail line.

“The Decision finds that HMLP’s existing system is susceptible to a townwide outage under certain contingency events, including the loss of a double circuit tower.  The Decision finds that the project is needed to maintain reliable electric service for the Town of Hingham and is superior to other transmission alternatives evaluated for cost, reliability, and environmental impacts.”

– MA Energy Facilities Siting Board

HMLP’s Reliability Project will address these significant reliability deficiencies by adding a new underground transmission line that will be fed by a new Eversource Tap Station in Weymouth, run underground in Weymouth and Hingham, and connect to a new, second sub-station located within the Hingham Transfer Station.

The Siting Board’s enabling statute charges the Siting Board with the responsibility to implement the Commonwealth’s energy policies to provide a reliable energy supply with a minimum impact on the environment at the lowest possible cost.

In its Final Decision, the Siting Board found that the HMLP Reliability Project “is needed to maintain a reliable supply of electricity,” and further noted that “the Siting Board finds that the Project is appropriate, and the record shows no alternative means is capable of solving the need or would be superior to the proposed project.”  The Decision also stated that “the Siting Board finds that the Project, as designed, will provide a reliable energy supply for the Commonwealth, with a minimum impact on the environment, at the lowest possible cost.”

As outlined in detail in the Siting Board’s 103-page Final Decision, before earning approval for the Project, HMLP was required to demonstrate the project meets the following requirements: ”(1) that additional energy resources are needed; (2) that, on balance, the proposed project is superior to alternative approaches in terms of reliability, cost, and environmental impacts, and in its ability to address the identified need, (3) that the applicant has considered a reasonable range of practical facility siting alternatives and that the proposed facilities are sited in locations that minimize costs and environmental impacts while ensuring a reliable energy supply, (4) that environmental impacts of the project are minimized and the project achieves an appropriate balance among conflicting environmental concerns as well as among environmental impacts, cost, and reliability, and (5) that plans for construction of the proposed facilities are consistent with current health, environmental protection, and resource use and development policies of the Commonwealth.”

Throughout an extremely detailed examination of every aspect of the Project that spanned almost two calendar years, the Siting Board held two public hearings, two evidentiary hearings, and required HMLP and Eversource to provide detailed responses to multiple questions on reliability standards, need, alternative projects, site and route selection, cost, and a wide range of environmental and construction impacts, including noise, traffic, visual, hazardous waste, wetlands, water resources, land use, air and magnetic fields.  The Siting Board offered the public numerous opportunities for input and discussion and required the submission of briefs from both HMLP and Eversource. 

Finally, the Decision includes multiple conditions that HMLP and Eversource must satisfy – both before and after construction of the Project.  

The Siting Board’s voting members include representatives from the Executive Office of Energy and Environmental Affairs, the Department of Public Utilities, the Department of Energy Resources, the Department of Environmental Protection, the Department of Fish and Game, the Director of Permit Regulatory Office, the Executive Office of Economic Development, the MA Department of Public Health, and two current public representatives, the Mayor of Beverly and the Town Manager of Barnstable.  The Siting Board has been reviewing transmission projects, gas pipelines, power facilities and battery projects in Massachusetts for 50 years using a rigorous technical and evidentiary process.

At the September 30th Siting Board meeting, DPU Chairman Jeremy McDiarmid stated that HMLP has “demonstrated need and has, [as] the record reflects, [there is] a close cooperation among the municipalities, among the HMLP and Eversource and the parties, and the conditions seem reasonable and appropriate for a project of this nature. I think it is well within keeping of the reliability of the system for the good folks of Hingham.”

What’s Next

Since 2020, HMLP has held or participated in over 40 public outreach meetings or events to share information, listen to concerns and answer questions about the HMLP Reliability Project.  On April 30, 2022, Hingham Town Meeting voters officially launched the Project by authorizing the Select Board to transfer land at the Hingham Transfer Station to HMLP for the new substation.

Now that the arduous state regulatory process has been completed, and state approval has been granted, local permitting will begin and project funding must be secured. 

Hingham Town Meeting – Spring 2027

Hingham residents will be asked to approve a long-term bonding component of the overall funding plan to bring a reliable energy supply to Hingham and eliminate the current risks of sustained power outages with the current energy supply system.

For more information about the HMLP Reliability Project, including a link to the Massachusetts Energy Facilities Siting Board’s Final Decision, please visit: www.heirp.com 